Environmental Impact Report, Corndale Quarry
Project Type: Assessment
Detailed Description: Pursuant to the provisions of State Environmental Planning Policy No. 37, the quarry was registered for an annual production rate of some 20,000 cubic metres. S J Connelly as Project Director documented a comprehensive statement of environmental effects seeking consent for expansion of the quarry so as to provide for output of approximately 50,000 cubic metres per annum. The key issues associated with this project related to noise and dust suppression, visual impact mitigation, rehabilitation works and onsite water management.
This project was the subject of Land and Environment Court proceedings. The IA documentation was supported by the Court in its judgement. This quarry now provides an important resource to the region.
Location – Lismore, NSW, Australia
Year – 1993
Client – Corndale Quarries Pty Ltd