EIS For Extractive Industry and Landfill, Badgerys Creek
Project Type: Assessment
This Environmental Impact Statement was prepared in association with other specialist consultants. The company proposed quarrying of clay/shale and sandstone/laminite over a 63 ha area at Badgerys Creek with the excavations being rehabilitated through backfilling with solid waste. The project site is just north of the then second Sydney Airport site in the City of Penrith.
An estimated 17 million tonnes of light and dark-firing clays and shales have been identified on the project site with a further six million tonnes of sandstone/laminite needed to be quarried to remove these materials.
Location – Sydney, NSW, Australia
Year – 1991 to 2001
Client – Camide Pty Limited